If a sewage system is predicted to handle more than 2000 gallons per day, what extra documentation is necessary?

  1. Only a site map

  2. Plans, specifications, soil data, and absorption test data with an engineer's seal

  3. A notarized statement of compliance

  4. Just a construction permit from the county

The correct answer is: Plans, specifications, soil data, and absorption test data with an engineer's seal

When a sewage system is predicted to handle more than 2000 gallons per day, it is necessary to provide detailed documentation to ensure the system's design meets health and environmental safety standards. This includes plans and specifications that outline how the system is designed, evidence of the soil's ability to accommodate the system through soil data, and absorption test data which demonstrates how well the soil can absorb effluent. The requirement for an engineer's seal indicates that a qualified professional has reviewed and approved the design, ensuring it is technically sound and compliant with relevant regulations. This level of documentation is crucial for systems of this size, as they can have a significant impact on the surrounding environment if not designed properly. The other options do not provide the comprehensive information needed for systems handling such large volumes of sewage.