How many days does the county board of health have to approve a construction permit for septic?

  1. 10 days

  2. 20 days

  3. 30 days

  4. 90 days

The correct answer is: 20 days

The county board of health is required by state regulations to act on a septic system construction permit application within a specified timeframe to ensure timely processing. In Georgia, the timeline for approval is set at 20 days. This period is designed to allow the health department to review the application adequately, consult with relevant environmental guidelines, and ensure that the proposed septic system complies with all local and state standards. By adhering to this timeframe, the county can provide a structured and efficient permitting process, which is essential for managing public health and environmental safety effectively.